How Long Does It Take to Switch Core Banking Platforms?



Switching to a new core banking system (CBS) is a major decision for any financial institution. Whether you're a traditional bank, a credit union, or a digital-only neobank, migrating to a modern core banking platform can significantly improve efficiency, customer experience, and scalability.


But one of the biggest questions banks ask is: "How long will this migration take?"


The answer depends on multiple factors, including the size of the institution, the complexity of operations, and the technology being adopted. In this blog post, we’ll break down the key stages of core banking migration and provide realistic timelines based on industry standards.


Factors Affecting Core Banking Migration Time

Before estimating the duration, it’s important to understand what influences the timeline:

  • Bank Size & Complexity

  • Small banks/credit unions: 6–12 months

  • Mid-sized banks: 12–24 months

  • Large banks with multiple products: 2–4 years


Type of Migration


  • Big Bang Migration (all at once) → Faster but riskier

  • Phased Migration (module by module) → Slower but safer


Legacy System Constraints

  • Older systems with outdated data structures take longer to migrate.

  • Regulatory & Compliance Requirements

  • Banks in highly regulated markets may face longer approval processes.

  • Vendor & Implementation Partner Efficiency


  • Experienced vendors can speed up deployment.



Typical Core Banking Migration Timeline

Here’s a general breakdown of how long each phase takes:


1. Planning & Vendor Selection (3–6 months)

  • Assessing business needs

  • Evaluating vendors (RFPs, demos, negotiations)

  • Finalizing contracts


2. System Configuration & Customization (6–12 months)

  • Setting up workflows, product definitions, and integrations

  • Customizing for local regulations

  • API integrations with third-party services


3. Data Migration & Testing (3–9 months)

  • Extracting, cleaning, and mapping legacy data

  • Running parallel testing (old vs. new system)

  • Security and performance testing


4. Training & Go-Live (1–3 months)

  • Staff training on the new system

  • Soft launch (pilot testing with a small customer group)

  • Full-scale deployment


5. Post-Migration Optimization (Ongoing)

  • Bug fixes, performance tuning

  • Additional feature rollouts



Real-World Examples

  • Neobanks & Digital Banks (e.g., Revolut, N26) → 6–12 months (cloud-native systems)

  • Mid-Sized Traditional Banks → 18–24 months

  • Large Banks with Multiple Legacy Systems → 3+ years


How to Speed Up Core Banking Migration?

Choose a Cloud-Based Core Banking System (e.g., Mambu, Thought Machine) – reduces infrastructure delays.

  • Adopt Agile Implementation – break migration into sprints.

  • Use Experienced Consultants – avoid common pitfalls.

  • Automate Data Migration – reduces manual errors.


Switching core banking platforms is a complex, multi-phase project, and rushing it can lead to costly failures. While smaller institutions can complete the process in under a year, larger banks should expect 2–4 years for a smooth transition.



 